Lewiston Port Details Revenue from Megaloads


The Port of Lewiston netted more than $500,000 from Imperial Oil megaloads in its most recent fiscal year.

The $500,772 figure was released in a recent audit of the port and was pointed out by David Doeringsfeld, the port’s manager.

The number doesn’t include another $396,233 in expenses the port had for the modules of a processing plant under construction in the Kearl Oil Sands of Alberta, Canada. Continue reading

Port of Lewiston Expansion Application Comments by Saturday


On Wednesday, a dozen regional anti-megaload activists attended and provided oral testimony at the U.S. Army Corps of Engineers public hearing about the Port of Lewiston expansion application.  Please lend an ear to the Thursday, October 20, KRFP Evening Report between 11:03 and 9:16 for a brief summary of the arguments presented by opponents and proponents of the Port’s proposal to gravel a storage yard, move a mooring dolphin, and extend the dock into the Clearwater River, explicitly to accommodate larger shipments.  Because most of the public comments voiced at the Lewiston hearing supported Port expansion, your comments are crucial to requesting a full environmental impact statement, accompanying public involvement, and ultimate denial of this expensive and short-sighted project.  Please peruse the previous WIRT Port of Lewiston Permit Application Comments for writing prompts.  The Corps has received 140 written comments to date: let’s double that number with your expansion-denouncing input by Saturday, October 29, at midnight.

(From WIRT Newsletter)

Port of Lewiston Expansion Hearing on Wednesday, October 19


The Walla Walla District of the U.S. Army Corps of Engineers will conduct a public hearing on October 19, 2011, to solicit addition information concerning the Port of Lewiston NWW-2010-00213 application to expand its existing facilities.  The proposed port actions could accommodate megaload shipments and require the Corps’ verification and authorization for work in federal waters, lands, and flood control structures (Lewiston levees).  Registration to comment and an informational open house hosted by Corps representatives begin at 6 pm, before the 7 pm hearing at Sacajawea Junior High School, 3610 Twelfth Street in Lewiston.

The Corps will record the hearing and report verbatim all written and oral comments at the meeting, for inclusion in the official public record.  Besides speaking out on Wednesday against this unnecessary development venture, please send your remarks to the Corps by the end of the extended public comment period on October 29, 2011.  For further information about public hearing procedures, comment submission addresses, and the port expansion project, see the Corps’ News Release and its Notice of Public Hearing.  Call Friends of the Clearwater at 208-882-9755 to carpool from downtown Moscow at 5:30 pm.

(From WIRT Newsletter)

Comment Period Extension for Port of Lewiston Expansion


With the possibility that Imperial Oil could ship megaloads up either or both highways coursing north from the Port of Lewiston, our public resource interests would best be served by constraining the capacity of the port to accept and store oil company modules at its facilities.  After all, it was the hearty welcome to the port by the Mega-ho governor and congressional delegation that foisted this looming industrial corridor hell upon us.  The good news is that the U.S. Army Corps of Engineers (Corps), who must consider any dock extension permit requested by the port due to its forays into public waters, has extended the public comment period another thirty days until August 22, 2011, perhaps due to our collective insistence.  So if you have not commented yet (perhaps due to WIRT’s late notice: Sorry!) or if you commented only on the overarching megaload situation encouraging port expansion (as detailed in Fighting Goliath’s forwarded talking points: Thanks!), you now have an (additional) opportunity to dissect and denounce the technical intricacies of the port’s expansion plan.  WIRT hopes to provide more information about these items later.  However, the bad news is that the Corps did not (yet!) offer public hearings addressing this port proposal, as many of us requested, and that the Port now also proposes laying foot-deep gravel on ten acres “to allow for additional storage area for equipment and miscellaneous products delivered to the port” (likely more megaloads).  Please see the brief public notice/permit application/project proposal, Port of Lewiston Expansion Permit Application, and WIRT’s submitted Port of Lewiston Permit Application Comments.  Send your comments about Application NWW-2010-213-Wpr (note different number) to the U.S. Army Corps of Engineers at PortofLewiston-PN@usace.army.mil.

(From WIRT Newsletter)

Port of Lewiston Expansion Plan Comments due Friday, July 22


The Port of Lewiston has applied to the U.S. Army Corps of Engineers for a permit to expand their dock facilities into the Clearwater River.  The Port is proposing this expansion explicitly to increase its capacity to accommodate larger equipment and oversize cargo, likely more oil-processing megaloads that haulers could transport on U.S. Highway 12 and/or U.S. Highway 95 and onward to the interstate system and the Alberta tar sands.  As a tax-payer funded project that could receive support amid ubiquitous budget crises, the expansion may also encourage later silt dredging in front of Port terminals and/or raising of the Lewiston dikes to offset possible flooding aided by ongoing silt accumulations.  Further discharge of dredged and fill materials into the river could adversely impact water quality.  This potential Port enhancement could also simultaneously buttress the economic viability of the four lower Snake River dams while further jeopardizing the recovery and restoration of wild salmonid and other fish populations in the Clearwater Basin.  All of these consequent conditions could precipitate myriad negative socioeconomic and ecological effects in our region.

Unless the Corps grants an extension, the 30-day public comment period for the Port’s expansion plan expires on Friday, July 22.  Please ask for an extension of the comment deadline that currently deters many regional residents who travel during the summer months from submitting comments.  Demand a series of public hearings in Lewiston and the affected highway corridor cities, during which public officials could share information and accept input.  Also tell Corps decision makers that the current environmental assessment for the Port’s plan is inadequate and that an environmental impact statement should be prepared to study the cumulative impacts of this project.  See the Port of Lewiston Expansion Permit Application and consider utilizing some or all of the preceding and following talking points provided by our allies All Against the Haul, Fighting Goliath, and Friends of the Clearwater.  Send your emailed concerns to the Army Corps of Engineers at PortofLewiston-PN@usace.army.mil or your mailed written comments to:

U.S. Army Corps of Engineers

Idaho Falls Regulatory Field Office

900 N. Skyline Drive, Suite A

Idaho Falls, Idaho 83402-1700 Continue reading